NEW QUESTION # 44
What is shown on the vertical axis of the burnup chart?

  • A. Iterations
  • B. Kanban states
  • C. Team names
  • D. Story Points

Answer: D


NEW QUESTION # 45
Business Rule Variations and Simple or Complex are techniques used for

  • A. Splitting user stories and features
  • B. Prioritizing the backlog
  • C. Testing finished functionality
  • D. Writing user stories

Answer: A


NEW QUESTION # 46
Who manages the Program backlog in SAFe?

  • A. Business Owners
  • B. Product Owner
  • C. Product Management
  • D. RTE

Answer: C


NEW QUESTION # 47
A self-organizing team does not interact with the organization.

  • A. FALSE
  • B. TRUE

Answer: A


NEW QUESTION # 48
In which backlog are features identified, prioritized, estimated and Maintained?

  • A. Portfolio backlog
  • B. Team backlog
  • C. Solution backlog
  • D. Program backlog

Answer: D


NEW QUESTION # 49
Which 2 of the below are common techniques for splitting stories into smaller ones?

  • A. Business Rule variation
  • B. High priority
  • C. INVEST
  • D. Simple or Complex
  • E. WSJF

Answer: A,D


NEW QUESTION # 50
How many SAFe configuration are defined?

  • A. Five
  • B. four
  • C. three
  • D. seven

Answer: B


NEW QUESTION # 51
Who directs the Agile team?

  • A. Project Manager
  • B. The Agile Team is self-organizing
  • C. Product Owner
  • D. Scrum Master

Answer: B


NEW QUESTION # 52
Which of the following are true for the System demo?

  • A. It happens once per PI, at the end of the PI
  • B. It is not mandatory to have all the functionalities tested before the demo
  • C. Features are functionally complete or "toggled" so as not to disrupt demonstrable functionality
  • D. Architectural Runway work in process is scaffolded and toggled

Answer: C,D


NEW QUESTION # 53
Scrum and Kanban cannot be used together - either of the two needs to be chosen to be implemented.

  • A. FALSE
  • B. TRUE

Answer: A


NEW QUESTION # 54
Velocity is

  • A. the rate (in story points) at which the team delivers
  • B. measurement for economic benefit
  • C. business value delivered (monetary)
  • D. average hours of work done by the team

Answer: A


NEW QUESTION # 55
How many elements form the Continuous Delivery Pipeline?

  • A. four
  • B. three
  • C. seven
  • D. five

Answer: A


NEW QUESTION # 56
PI Objectives are business summaries of what each team intends to deliver in the upcoming Pl.

  • A. FALSE
  • B. TRUE

Answer: B


NEW QUESTION # 57
How many are the SAFe Lean-Agile principles?

  • A. ten
  • B. five
  • C. twelve
  • D. Four

Answer: A


NEW QUESTION # 58
What does the Continuous Delivery Pipeline enable?

  • A. Release on Demand
  • B. Annual Release
  • C. Scheduled Releases
  • D. Quarterly Release

Answer: A


NEW QUESTION # 59
SAFe Lean-Agile principles support centralised decision-making.

  • A. FALSE
  • B. TRUE

Answer: A


NEW QUESTION # 60
......