NEW QUESTION # 31
Reliability efforts, such as reliability centered maintenance (rcm), can be linked with rbi, resulting in an integrated program to

  • A. To reduce risk by mitigation activities
  • B. Reduce operating time of a unit
  • C. Reducedowntime in an operating unit

Answer: C


NEW QUESTION # 32
Act of mitigating a known risk to a lower level of risk.

  • A. Risk reduction
  • B. Risk mitigation
  • C. Risk management

Answer: A


NEW QUESTION # 33
No deterioration found in the inspection program but still failure can occur under the following conditions.

  • A. All the above
  • B. During plant construction period
  • C. As a result of change or process upset condition

Answer: C


NEW QUESTION # 34
If a qra has been prepared for a process unit, the analysis can borrow extensively from this effort.

  • A. Rbi probability
  • B. Rbi likelihood
  • C. Rbi consequence

Answer: A


NEW QUESTION # 35
Systematic use of information to identify sources and to estimate the risk

  • A. Risk
  • B. Hazard analysis
  • C. Risk analysis

Answer: C


NEW QUESTION # 36
Provides a basis for risk evaluation, risk mitigation and risk acceptance

  • A. Risk identification
  • B. Risk evaluation
  • C. Risk estimation

Answer: C


NEW QUESTION # 37
Termination of the ability of a system, structure, or component to perform its required function of containment
of fluid (le loss of containment)

  • A. Risk
  • B. Failure
  • C. Outcome

Answer: B


NEW QUESTION # 38
Risk evaluation is defined as the process used to:

  • A. assign values to the probability and consequence of risk.
  • B. compare estimated risk against given risk criteria.
  • C. select and implement measures to modify risk.
  • D. find, list, and characterize elements of risk.

Answer: B

Explanation:
As defined in API 580, Section 3.1.59:
"Risk evaluation: The process used to compare the estimated risk against given risk criteria to determine the significance of the risk." This follows from the broader risk assessment process where risk identification and analysis occur first, followed by risk evaluation.
Reference: API 580, 2nd Edition (2016), Section 3.1.59


NEW QUESTION # 39
The type of failure mode that likely to occur due to pitting

  • A. Catastrophic rupture
  • B. Small holes to ruptures
  • C. Cracks
  • D. Small hole sized leaks

Answer: D


NEW QUESTION # 40
FILL BLANK
_________ produces inspection and maintenance plans for equipment that should be implemented to provide ____________

Answer:

Explanation:
RBI, reliable and safe operation


NEW QUESTION # 41
Rbimay include methodologiestoassess the effectiveness ofthe management systems in maintaining

  • A. Plant integrity
  • B. Total asset integrity
  • C. Mechanical integrity

Answer: C


NEW QUESTION # 42
Following is the unit of measure of consequence that is least developed among those currently used for RBI assessment.

  • A. Affected area
  • B. Safety
  • C. Environmental damage
  • D. Cost

Answer: C


NEW QUESTION # 43
In the determination of risk, what values are often used when COF and/or POF data are not available?

  • A. Sensitivity analyses
  • B. Estimates of total risk by subject matter experts
  • C. Similar losses reported by insurance companies or jurisdictions
  • D. Assumptions or estimates of input

Answer: D

Explanation:
Section 11.5 of API 580 clearly states:
"Assumptions or estimates of input values are often used when consequence and/or POF data are not available." This allows an RBI team to proceed with analysis in the absence of complete data while noting that all assumptions must be documented and agreed upon to avoid misrepresentation.
Reference: API 580, 2nd Edition (2016), Section 11.5


NEW QUESTION # 44
For qualitative rbi analysis it us important to establish a set of rules to assure consistency in

  • A. Ranking
  • B. Categorization or classification
  • C. Segregation

Answer: B


NEW QUESTION # 45
The type of failure mode that likely to occur due to mechanical and metallurgical deterioration

  • A. Small holes to ruptures
  • B. Catastrophic ruptures
  • C. Cracks
  • D. Leaks

Answer: B


NEW QUESTION # 46
The amount and type of codes and standards used by a facility can have

  • A. No impact on RBI results
  • B. Significant impact on RBI results
  • C. Less significant impact on RBI results

Answer: B


NEW QUESTION # 47
Which of the following is a tool used to show the effectiveness in depicting a combination of events that could result in a loss of containment event?

  • A. Dual-mode model
  • B. LOC model
  • C. Logic model
  • D. Physical model

Answer: C

Explanation:
According to API 580, Section 3.1.28, the definition is clearly stated:
"Logic model: A tool used to depict the effectiveness in depicting a combination of events that could result in a loss of containment event." While a physical model (Option A) may represent the progression of release events, and other options (B and D) are not defined within API 580, only a logic model fits the definition used in RBI methodologies to evaluate event combinations leading to failure.
Reference: API 580, 2nd Edition (2016), Section 3.1.28
-


NEW QUESTION # 48
Following are the critical variables for deterioration mechanism except

  • A. Insulation
  • B. Process operating
  • C. Material of construction
  • D. Start up and shut down conditions

Answer: A


NEW QUESTION # 49
Some failures have potentially serious consequences, but if the probabilityof the incident is low, then

  • A. The risk may not warrant immediate action
  • B. The risk may warrant appropriate mitigation action
  • C. The risk may warrant immediate action

Answer: A


NEW QUESTION # 50
No deterioration found in the inspection program but still failure can occur under the following conditions.

  • A. All the above
  • B. During plant construction period
  • C. As a result of change or process upset condition

Answer: C


NEW QUESTION # 51
__________ is not a substitute for a process hazards analysis (PHA) or HAZOP

  • A. PHA
  • B. HAZOP
  • C. REM
  • D. RBI

Answer: A


NEW QUESTION # 52
......


Who should take the API-580 exam

The API Risk Based Inspection API-580 Exam certification is an internationally-recognized validation that identifies persons who earn it as possessing skilled as Risk Based Inspection Certification. If a candidate wants significant improvement in career growth needs enhanced knowledge, skills, and talents. The API Risk Based Inspection API-580 Exam certification provides proof of this advanced knowledge and skill. If a candidate has knowledge of associated technologies and skills that are required to pass API Risk Based Inspection API-580 Exam then he should take this exam.

 

Exam Valid Dumps with Instant Download Free Updates: https://www.testsdumps.com/API-580_real-exam-dumps.html

Fast Exam Updates API-580 dumps with PDF Test Engine Practice: https://drive.google.com/open?id=1zKeM5NGGGDDukpmU9nwsDeNvhLyIYJx9