[2023] Pass your NACE-CIP2-001 exam with this 100% Free NACE-CIP2-001 Braindump
View All NACE-CIP2-001 Actual Exam Questions, Answers and Explanations for Free
NEW QUESTION 39
Inspection and Test plans are developed by referencing:
- A. The Specification, Application Guidelines, 'Relevant Standards and Codes
- B. The Specification, SDS, relevant Standards and Codes
- C. The Specification, TDS, relevant Standards and Codes
- D. The Specification, Safety Manual, Relevant Standards and Codes
Answer: C
NEW QUESTION 40
The cost of qualified Coating Inspection is normally offset by:
- A. Lower Supervision Costs
- B. Lower Coating Life Cycle Costs
- C. Lower Safety Enforcement Costs
- D. Lower Application Costs
Answer: B
NEW QUESTION 41
Which surface preparation method uses a dilute acid solution to remove laitance and I roughen the concrete surface?
- A. High-pressure water washing
- B. Acid etching
- C. Sacking
- D. Stoning
Answer: B
NEW QUESTION 42
When observing design defects the NACE Inspector should:
- A. Stop the job immediately
- B. Request that the item be rebuilt with a better design for coating
- C. Ignore the defect as the inspector can't change the design
- D. Document the defect and the potential problems that could result
Answer: D
NEW QUESTION 43
It is always possible to see moisture on a steel substrate:
- A. True
- B. False
Answer: B
NEW QUESTION 44
When performing testing in accordance with ASTM D 2583 the inspector may observe:
- A. Adhesion failure
- B. Glue failure
- C. Cohesion failure
- D. Cold flow or creep
Answer: D
NEW QUESTION 45
You are the NACE Coating Inspector on a tank lining project and are asked to perform a high voltage holiday test after the coating applicators have completed their final repairs. After meeting all the confined space entry permit you enter the tank and notice a very strong odor of solvent.
Your first course of action should to:
- A. Exit the tank and immediately and report the problem to the nearest safety supervisor
- B. Exit the tank and document the incident in your daily report
- C. Don your air supplied respirator and continue the testing
- D. Investigate to find the source of the odor
Answer: A
NEW QUESTION 46
Coating Surveys are legally required:
- A. On high pressure gas lines and fireproofed structures
- B. On food and beverage vessels and can linings
- C. On water tanks and potable water pipelines
- D. On commercial marine vessels and offshore platforms
Answer: D
NEW QUESTION 47
You are the NACE Level 2 Coating Inspector where SSPC PA 2 has been specified with an additional requirement that no individual gauge reading shall be below a certain value.
As this is not part of the standard you should:
- A. Enforce the additional requirement
- B. Ignore the additional requirement
- C. Call your supervisor
- D. Request clarification from the specifier
Answer: A
NEW QUESTION 48
When completing the Final Inspection report the Inspector should write the report using:
- A. Language that only technical experts would understand
- B. Language that only in the project would understand
- C. Language that the most would understand
- D. Language that another NACE Inspector would understand
Answer: C
NEW QUESTION 49
You should bulk store coatings containing isocyanates
- A. in a refrigerated warehouses
- B. in a well ventilated area separate from the work place.
- C. in a heated warehouse.
- D. wherever it is convenient
Answer: B
NEW QUESTION 50
You are a NACE Level 2 Coating Inspector who has just arrived on a job in progress where there is no Inspection and Test Plan (ITP). The first morning you arrive the job is behind schedule and you are asked to take DIY Film Thickness readings.
Your FIRST preferred course of action is to:
- A. Call your supervisor
- B. Use a generally accepted industry standard and to take readings
- C. Develop your own methodology and proceed take the readings
- D. Refuse to take readings until an is in place
Answer: B
NEW QUESTION 51
Antifouling coatings are regulated by international treaties.
- A. False
- B. True
Answer: B
NEW QUESTION 52
The HATE adhesion tester uses
- A. compressed air to apply pressure to the test dolly.
- B. a special tape to apply pressure to the test dolly.
- C. mechanical means only to apply pressure to the test dolly.
- D. a hydraulic piston to apply pressure to the test dolly.
Answer: D
NEW QUESTION 53
A reinforced coating is
- A. less resistant to movement, abrasion, and impact than a non-reinforced coating.
- B. equally resistant to abrasion and impact as a non-reinforced coating.
- C. equally resistant to movement and impact as a non-reinforced coating.
- D. more resistant to movement, abrasion, and impact than a non-reinforced coating.
Answer: D
NEW QUESTION 54
The coating applicator has ignored a enface preparation hold point and applied coating over the surface without a sign off from you as the inspector.
Your FIRST preferred course of action is to:
- A. Advise the Owner and write a Non-Conformance report
- B. Require the Applicator to remove the coating
- C. Ignore the situation
- D. Stop the job
Answer: B
NEW QUESTION 55
When using a destructive Paint Inspection Gauge the NACE inspector must:
- A. Determine the Dry Film Thickness of the coating prior to use
- B. Ensure the glue on the dolly is properly applied prior to use
- C. Consult SSPC Guide 1 prior to use
- D. Select the appropriate hand wheel based on the measured Dry Film Thickness prior to us
Answer: A
NEW QUESTION 56
When working with someone who is very concerned about Stability and maintaining adherence to the status-quo, the Inspector should try to:
- A. Implement immediate to get them motivated
- B. Make sure they are the center of attention in all site meetings
- C. Give them as much advance notice as possible about upcoming changes
- D. Challenge their value to the team and try to get them out of their comfort zone
Answer: C
NEW QUESTION 57
External coatings applied to buried pipelines are generally tested for:
- A. Chalking resistance
- B. Solvent resistance
- C. Gloss level
- D. Cathodic disbondment
Answer: D
NEW QUESTION 58
WJ-1 is always performed using UHWJ at pressures above 210 MPa (30,000 PSI)
- A. False
- B. True
Answer: B
NEW QUESTION 59
When conducting inspections the Inspector should follow which standards:
- A. Australian standards in Australia
- B. NACE and SSPC standards in North America
- C. The specified standards
- D. ISO standards in Europe and Asia
Answer: C
NEW QUESTION 60
NACE Standards include:
- A. a) only
- B. Material Requirements
- C. a) & b)
- D. Standard Practices
Answer: C
NEW QUESTION 61
Inspection and Test Plans are provided to:
- A. So the Inspector doesn't have to read the entire specification
- B. So the contractor has a single document to reference
- C. Outline the inspection steps, sequencing and pass/fail criteria
- D. To supersede the requirements of the product data sheets
Answer: C
NEW QUESTION 62
The most likely area of failure on a buried external pipeline coating is the:
- A. Mainline coating
- B. Areas exposed to Ultra Violet light
- C. Field joint coating
- D. Ground bed
Answer: C
NEW QUESTION 63
......
NACE-CIP2-001 dumps Free Test Engine Verified By It Certified Experts: https://www.testsdumps.com/NACE-CIP2-001_real-exam-dumps.html
NACE-CIP2-001 Exam Free Practice Test with100% Accurate Answers: https://drive.google.com/open?id=18ajfcFWGJjsRKvd4LDEdAHMqZrKgDo9R